RUSHYDRO COMPLETED CONSTRUCTION OF THE PEVEK-BILIBINO POWER TRANSMISSION LINE

5 december 2024

In the Chukotka Autonomous Okrug, RusHydro completed, ahead of schedule, the construction of the second single-circuit 110 kV Pevek-Bilibino power transmission line, 496 kilometers long.

The new power transmission line connected the towns of Pevek (the northernmost town of Russia) and Bilibino. The OHL construction is of great importance for the region. It will ensure reliable power supply to consumers in the Chaun-Bilibino energy district, improve the quality of life of the population and create conditions for industrial development. The new power transmission line replaced the existing OHL on wooden towers built in the 1960s that has reached the ultimate degree of wear.

The construction project of the two single-circuit 110 kV Pevek-Bilibino overhead power lines was implemented in two stages. The first stage included the construction of the first OHL circuit, erection of the 110 kV Bilibino distribution point with two transformers with a total capacity of 12.6 MVA, and reconstruction of the 110/35/6 kV Komsomolsky substation. The second stage included the construction of the second OHL circuit, reconstruction of the 110 kV Yuzhny substation, and a new construction of the 110
kV Beta switching substation. The first OHL was solemnly put into operation from the site of the Eastern Economic Forum in 2023.

Construction under the second stage commenced at the end of 2021. The power transmission line was built under extreme natural and climatic conditions in a remote and hard-to-reach territory belonging to the Far North regions. The required construction materials were delivered by sea along the Northern Sea Route during the navigation season, with the major construction and assembly works carried out in winter.