RUSHYDRO COMPLETED CONSTRUCTION OF UST-SREDNEKANSKAYA HPP

5 december 2024

Construction of the Ust-Srednekanskaya HPP on the Kolyma river in the Magadan Region has been completed. All HPP structures have been erected within design parameters, equipment has been installed and tested, the water reservoir has been filled. The certificate of energy facility acceptance into permanent operation has been signed by the acceptance committee.

The Ust-Srednekanskaya HPP with a capacity of 570 MW is located downstream of the Kolymskaya HPP and is the second link in the Kolymskaya chain. The unique hydropower facility was built in extremely difficult environmental conditions – the thickness of permafrost at the plant site is 300 m, and the air temperature drops to minus 60 °С in winter.

The plant buildings include an earth dam with a length of 2,100 m and height of 65 m, three concrete dams with a total length of 325 m and height of 74 m, HPP building with four hydroelectric units with a capacity of 142.5 MW each. The turbines and generators of the Ust-Srednekanskaya HPP were manufactured by the Russian company Power Machines.

The plant will generate an average of 2.55 billion kWh of environmentally friendly, renewable electric energy annually. The plant construction significantly increased the reliability of the electricity supply in the isolated Magadan power system, and provided electricity for new production sites, such as Natalkinsky MPP, the largest gold mining project in Russia. As part of a chain, the Ust-Srednekanskaya HPP will enable waterborne traffic on the Kolyma river and lift the operating regime restrictions at the Kolymskaya HPP, the largest power plant in the Magadan Region.

The Ust-Srednekanskaya HPP construction project was developed by the Lengidroproekt Institute in the 1980s. The site preparation began in 1991, but the construction process was slow due to lack of financing. In 2008, after the plant was handed over to RusHydro, the plant construction accelerated.

In 2011, the Kolyma river was dammed. In 2013, the first two hydropower installations were commissioned, operating at a decreased water pressure, with temporary turbine runners, with a capacity of 84 MW each. In 2019, the third hydroelectric unit was commissioned with a capacity of 142.5 MW. In 2021, the temporary turbine runners of the first two hydroelectric units were replaced with standard ones, increasing the plant capacity by 117 MW. In 2022, after the last hydroelectric unit was launched, the Ust-Srednekanskaya HPP reached its design capacity of 570 MW. The plant construction was carried out by JSC Ust-SrednekanGESstroy, a company controlled by RusHydro.

As part of the construction project implementation, RusHydro has built a new district hospital building and a Folk Art and Cultural Recreation Center in the urban-type settlement of Seymchan in the Srednekansk District of the Magadan Region. To increase the fishery resources of the Kolyma river, the Company plans to build a fish hatchery.