MODERNIZATION OF THE EZMINSKAYA HPP HAS BEEN COMPLETED

27 november 2024

RusHydro has completed a large-scale modernization of the Ezminskaya HPP in North Ossetia. The work has been carried out as part of the implementation of the Program of Complex Modernization of RusHydro.

In 2024, the Ezminskaya HPP located on the Terek river celebrated its 70th anniversary since the commissioning of the first hydroelectric unit. During operation, the HPP equipment served out its standard service life, became obsolete and reached the high degree of wear by virtue whereof RusHydro made a decision on a comprehensive modernization of the plant with the replacement of all equipment and major repairs of hydraulic structures.

During modernization, all three hydroelectric units of the plant were completely replaced with more efficient ones, which made it possible to increase the HPP power from 45 to 60 MW. The hydromechanical equipment (gates, trash-rack structures and their drives), the overhead crane of the machine hall, power transformers, switchgear equipment, auxiliary and electrical equipment were also completely replaced.

The hydraulic structures underwent major repairs with the replacement of the areas with weakened concrete at the head unit, in the diversion tunnel more than 7 km long, the diversion channel, the daily runoff pond, the headwater pond, the wastewater outlet, and the tail channel. The hydro power plant building was renovated, its historical appearance remained unchanged. The slope under the penstocks was strengthened, and a modern anticorrosion coating was applied to the penstocks themselves which, according to the survey results, are in good condition.

The project for the modernization of the Ezminskaya HPP was developed by the All-Russian Scientific Research Institute of Hydraulic Engineering named after B. E. Vedeneev, the general contractor for the modernization is JSC Hydroremont-VCC, both organizations are subsidiaries of RusHydro.

RusHydro is implementing the Program of Complex Modernization of hydropower facilities, which plans to replace half of the turbines, generators and transformers at its HPPs and PSHPs. Such a large-scale program of upgrading obsolete and worn-out equipment is unique and unprecedented for the domestic power industry. It is distinguished by a focus not on selective replacement of individual units and assemblies, but on a complex modernization of hydropower generation facilities as single technological systems, with the replacement or upgrade of the main and auxiliary equipment, common plant service systems and hydraulic structures.

Over 12 years of the PCM, the increase in the installed capacity of RusHydro’s hydro power plants amounted to 631.5 MW, which can be compared to another large HPP added to the energy holding. 144 hydro turbines, 147 generators, 105 power transformers as well as over 10,000 units of auxiliary equipment have been replaced or upgraded over this time.